At the foot of Main Street, the fishing pier is now just pilings. The City of Dunedin finished taking down the storm-damaged pier above the waterline in early summer 2026. The new pier, which was contracted in January, still can't be built until permits arrive. A few hundred feet away, boats are back in their slips and Olde Bay Café is serving. Six charter operators are running trips from the commercial docks.
Parts of the Dunedin Marina are working again, and parts are still fenced off. It is reopening in a set order, and the City has written that order down. The people who rent space and pay for the marina come back first. The public pieces, meaning the boat ramp, the day docks and the fishing pier, come last. Once you know that order, this fall's waterfront makes more sense.
The City's Marina Restoration Update on Engage Dunedin was last updated October 5, 2026. Read top to bottom, it shows the sequence.
On its main Marina page, the City says it cannot yet estimate how long the closure will last. Commercial charters, Olde Bay Café and boating classes keep running in the meantime. The charters listed are A Boat Day, Daisy Mae Fishing Charters, Done Gone Dunedin Tours, Dunedin Sailing Charters, Nomadic Fishing Charters and ParrotDise Express Boat Tours.
The order lines up closely with how the marina is funded. Slip rents pay for the marina's day-to-day operations through the Marina Enterprise Fund. In January 2023 the City's consultant, Raftelis, recommended five 10% increases to keep that fund self-sustaining. The first took effect April 1, 2023, and more followed on October 1, 2024 and October 1, 2025. Tampa Bay Beacons reported that the fourth increase, which took effect October 1, 2026, came in at 7% instead of 10%. Commissioners said a $3 million state appropriation for hurricane repairs made the difference.
The City's restoration page breaks down each project's budget. The figures below are exactly as the City lists them, so the pier's shares come out one cent off its total.
| Project | Total | FEMA share | State Disaster Fund | Local share | Where it stands |
|---|---|---|---|---|---|
| Bulkhead and seawall | $3,500,000 | $2,625,000 | $437,500 | $437,500 Marina Fund | East wall underway, fall 2026 target |
| Fishing pier, day docks, emergency docks | $2,139,238.91 | $1,604,429.18 | $267,404.87 | $267,404.87 General Fund | Demolition done, waiting on permits |
| Docks A and B | $5,000,000 | $3,750,000 | $625,000 | $625,000 Marina Fund | Permitting began May 2026, construction expected 2028 |
The FEMA figures are estimates. The City says it is still pursuing reimbursement. The pier also has a separate $1.5 million state appropriation set aside to cover part of its cost. The City says the $3 million in the state's FY 2026–27 budget will go toward resilient infrastructure, such as floating docks, that FEMA does not cover.
Finance Director Les Tyler told the Beacons the plan holds "as long as FEMA fully reimburses us." If it doesn't, he said, the City may have to look at adjusting slip rates in the future. In short, slip holders' rents carry the marina's operating budget and part of its storm risk. The pier is the one piece with a General Fund share instead of a Marina Fund share, and it is also the piece still waiting on federal permits.
The same split between the public side and the paying side shows up a mile north on the road to Honeymoon Island. Pinellas County's Dunedin Causeway bridges project page, updated July 13, 2026, lists its Helene repairs as complete. That work covered the access road, the movable-bridge fenders, the tide-relief bridge and the bag walls. A City release from September 4 says the causeway has been closed since 2024 because of Milton damage, and that County repairs are expected to finish by December.
A separate County maintenance project will take longer than both. That work replaces bridge steel coatings and damaged structural steel and is expected to last until about winter 2027. During it, the bridge opens only one leaf, with six feet of clearance on the down span, and there may be temporary lane closures. If you run a boat with any height through that channel, the bridge-opening limit matters more right now than the December date.
The causeway is also getting new rules. At its September 3 meeting, the City Commission voted 5-0 to adopt an ordinance banning the launch of motorized watercraft from the south side of the causeway. Launching was already banned on the north side, west of the drawbridge. The City says the ordinance does not affect operating motorized boats in the Intracoastal Waterway or St. Joseph Sound.
With the ramp closed, parking near Edgewater Park blocked and the pier waiting on permits, most of the late-October and November events are in the parks a few blocks back from the water. One series is still right on the waterfront.
Piper on the Pier brings a bagpiper to Marina Plaza at sunset, at 148 Marina Plaza. Remaining dates are October 23, 24, 30 and 31, and November 6, 7, 13, 14, 20 and 28.
The rest of the season, by date:
The market change in November is the one most likely to shift your weekly routine. Starting in November, the Downtown Market moves to Pioneer Park on both Fridays and Saturdays, 9 a.m. to 2 p.m., and keeps that schedule through December. The History Museum lot it leaves is just down Main Street from Monkey Mike's, the dipped frozen banana and dessert shop at 369 Main St. that the Tampa Bay Times covered in August.
Several dates fall within the next ten weeks. The east seawall is due in fall 2026, and once it's done the parking and drive aisle by Edgewater Park should reopen. The City is aiming to reopen the boat ramp in 2026, but it hasn't named a date, and the ramp will come back under new rules. The County expects the causeway repairs to finish by December. Slip holders can buy 2027 parking permits at the Harbor Master Office starting in December.
Downtown parking won't change for a while. The Douglas Parking Center at 968 Douglas Ave. is the first phase of Main Street Exchange, and its garage is planned to open in 2027. Pinellas Trail access next to the site is staying open during construction. Until then, the City asks anyone heading to the marina to expect limited public parking. For questions about the marina itself, the Harbormaster's Office is at 727-298-3030.
If you own a waterfront home or keep a boat on the Dunedin side of the bay, these repair schedules affect daily life, and they will affect value whenever you decide to sell. At Aquamarine Real Estate, we track how waterfront access is recovering around Tampa Bay, as we did with Safety Harbor's pier and marina. We're glad to talk through what it means for your property. Schedule Your Complimentary Consultation.
Stay up to date on the latest real estate trends.
You’ve got questions and we can’t wait to answer them.